Viaduct executed above piers with height exceeding 100 m (the highest with 114m high) with an underslung Movable Scaffolding System
Extension of the Deck width executed with a tabs machine form adapted from a form traveller system from CONSTRUGOMES
Deck construction in three stages: Box with movable scaffolding (two phases); extension with tabs machine (one phase).
The concreting cycle expected was 10 days per span, but it was reached a 7 days/ span cycle.